Animal Shelter Construction Update

Print
Press Enter to show all options, press Tab go to next option

animal shelter rendering

After years of careful planning and design, in late May 2017, the City of El Cajon began construction of the new El Cajon Animal Shelter. 

The El Cajon Animal Shelter, a 14,703-square-foot one-story building with a 2,600-square- foot exterior, will include administrative offices, housing for animals, veterinary services for sick and injured sheltered animals, grooming, play/interaction areas, pet adoption services, an exercise area, and more. The new shelter doubles the size of the current 50-year-old shelter, located nearby at 1275 N. Marshall Avenue.

The modern facility will cost approximately $9.3 million and is funded by Proposition O special revenues, the half-cent sales tax increase approved by voters in November of 2004 specifically for improvements to public safety facilities and a new animal shelter.  The special tax ended in 2015.

Ferguson Pape Baldwin Associates are providing project architectural services and CW Driver is the general contractor providing construction management services.

The shelter is expected to open by the summer of 2018!

 


dog pawProgress of Construction dog paw


 

NOVEMBER 2017

We are excited to announce project construction is now 40% complete!  Overhead ductwork and plumbing as well as in-wall plumbing and electrical installation is on-going. West storefront entrance construction has commenced.  Crew started installing dry wall.   Kennel manufacturing and installation, shelter flooring and tile, X-ray room, PA System, and the Shelter’s donor feature are all being worked on behind the scenes.  Door frames have been installed, interior metal framing has been completed, and wall insulation is almost finished.

 animal nov 9  animal nov 13
    November 9, 2017       November 13, 2017
 nov 15  animal nov 15a
    November 15, 2017       November 15, 2017


 

OCTOBER 2017

The construction of the new shelter has been AMAZING!  Roof framing, interior metal stud framing, and in-wall plumbing has commenced.  Gutter systems, wall sheathing, weather barriers, and roofing panels have been installed.  Closures for metal roofing is underway and interior electrical continues to be installed as the project progresses.

 Oct 3, 2017  oct 17, 2017
    October 3, 2017       October 17, 2017
 oct 24, 2017  oct 24, 2017 (2)
    October 24, 2017       October 24, 2017


 

SEPTEMBER 2017

Rapid development continues on the construction site during the month of September!  Concrete floor slabs have been poured at grade level.  Concrete masonry is complete and the majority of steel and carpentry framing are nearly finished. Overhead plumbing, electrical and fire protection piping has begun with the roof to be stocked and installed next month.  

 ANIMAL SHELTER CONSTRUCTION sep01  ANIMAL SHELTER CONSTRUCTION sept14
    September 1, 2017       September 14, 2017
 animal shelter sept 22  animal shelter sept 28
    September 22, 2017     September 28, 2017

 

AUGUST 2017

The progression of construction does not cease to amaze us! Despite the recent heat wave, crews have been working hard and finished building the masonry walls and started work on the sub-foundation  infrastructure.  The utility route planning is almost near completion.  Foundation is scheduled to pour next month.

 81  82
     August 2, 2017      August 9, 2017
 83  84
     August 10, 2017      August 18, 2017


 

JULY 2017

After less than a month of grading, the foundation has been formed and the walls began to be built for the new Animal Shelter.  Despite the hot weather, construction has progressed rapidly and the visible activity has been exciting to watch.  What cannot be seen in the photo is the installation of sewer lines and storm drains and the pouring of the building’s foundation, all of which has been momentously accomplished in July.

 71  72
      July 3, 2017       July 12, 2017
 73  74
     July 14, 2017       July 17, 2017


 

JUNE 2017

Contractors hit the ground running! The site was graded for the building pad, footings were installed and utility installation began.

 61  62
     June 6, 2017      June 15, 2017
 63  64
     June 20, 2017      June 28, 2017


 

MAY 2017

It’s been more than12 years in the making….the moment we’ve all been waiting for!

A Groundbreaking Ceremony was held on May 23, 2017, marking the start of construction of El Cajon's new Animal Shelter. Work activities began on-site the week of May 29th.

 ANIMAL SHELTER GROUNDBREAKING 1 5-24  ANIMAL SHELTER GROUNDBREAKING 1 5-24
     May 23, 2017       May 23, 2017
 ANIMAL SHELTER GROUNDBREAKING 1 5-24  ANIMAL SHELTER GROUNDBREAKING 1 5-24
     May 23, 2017       May 30, 2017

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer